The first week of the official start of  the Balmoral Renewal Project has commenced with good progress.
  • work has begun marking out and preparing the new site for the Rural Shed following the approval of the DA
  • work has commenced to repair the underground damaged electrical wiring throughout the property destroyed by the fires
  • many of the wooden walkways around the property were fire damaged , work has commenced replacing the burnt wood
  • work has commenced in replacing some of the damaged water pumps as part of moving and  establishing a dedicated pump house
  • work to upgrade the caretakers kitchen is moving ahead
  • decoration work to Shri Mataji’ cottage has also been undertaken
  • attached is a photo of the destroyed entrance gate, work to prepare footings for the new masonry gate have commenced.
 